GAIL GAS Update log
The project was initially launched by Pavithran working with information from his contacts that GAIL has launched the service in 2018. However after a few electrical issues the work was stopped in 2019, Covid being another dampner to the initiative.
We thank Ananth sir for organising the sheet and sharing the same with the community
There are a few flats which are not listed accurately in the list, we request owners to kindly review their details in the sheet provided. Incase of any discrepancy, please fill out the form listed above. https://forms.gle/rmVyHNca8AXDG9FG6
Please note that this is being done on best efforts basis, we are only enablers in the process. The ownership of transaction for your apartment with GAIL is under your respnsibility and accountability.
Appendix A: JMR Form - please store for long term reference (in your email / safe storage)
Notices issued by SCMC/JLL:
02/Aug/2025:
Photos of work in progress:
13/Aug/2024: GAIL Gas meters being installed in A1 Block
04/Aug/2025: 2PM: Riser pipe work started in A Blocks (will be working without break to deliver asap)
26/Jul/2025: Gail gas pipeline T-connection and riser work is currently in progress at the site for A Block GAIL Gas subscribers
Background:
Way back in 2018, Pavithran (Sugruha board member) had received information from his friend in MECON who was a consultant for GAIL Gas that GAIL is supplying piped natural gas to apartment complexes. This project was initiated with full force, and homes were fitted with meters etc. However, due to technical issues and COVID hitting us, this progress was halted.
Page Created & Updated by : Smaran Mudbidri, Secretary(2024-25), SUGRUHA Created on 18/Jun/2025