Regular updates, to reduce whatsapp traffic, GAILGAS proceeds will be updated on this page.
Link to this page: https://sugruha.in/index.php/2015-08-23-04-41-55/for-residents/221-documentation
Link to South City GAIL Gas Updates Whatsapp group: https://sugruha.in/index.php/2015-08-23-04-41-55/for-residents/221-documentation
-09/Oct/2025: Followed up with GAIL on the pipelines laying outside for 1+ KM to confirm if this work is pending / is it excess pipe. This would help gain an understanding of the time it is expected to take. Also requested that though we are all eagerly waiting for GAIL Gas, that safety and procedure not be compromised. Also understand that Ex-Corporator M Jayaram and MLA Shri M Krishnappa have been following up, on a regular basis, with GAIL to ensure any impedements are cleared up and have requested prioritizing South City.
- 08/Oct/2025: The escalation to the MP and GAIL Gas seems to have resulted in expediting work over the past 1 week by deploying additional staff working in shifts around the clock and over public holidays to cover the overall length of the pipeline. The pipeline can be seen installed up to Nayara petrol pump with GAIL Stones along the road sides on the Brigade Millenium road.
GAIL has reported to have completed the pipe laying work from Nayara petrol pump upto South City barring a 90 meter gap near a Nala / bridge at Naraya Petrol Pump, where they faced some local challenges, which they have overcome, and also with BESCOM as they are identifying electric wire paths - requiring them to proceed with caution. This work involved takes only 7 to 8 days, however given the complexity, its subject to obstacles they may face. They realistically expect to complete the pipe work before the 19th of October 2025.
I have requested the GAIL senior member today to request inspecting flats having pending meter / internal pipe installation work and necessary work be planned with the resident. Earlier, GAIL was apprehensive where they had to drill through expensive interiors as this is not in their scope and they cannot take responsibility for damages. This has to be worked between the resident and the GAIL team. Therefore during inspection the GAIL team/official may request drilling / other arrangements to be done by the resident in working with resident's vendors should they see an issue undertaking this work. This is purely a decision to be taken by the resident SCMC/Sugruha has no advise/suggestions/responsibility in this regard.
Also, given that the pipeline pieces are still seen near the Mini Forest Road and the South City - Balaji Service Station road, that an inspection be made to confirm that the pipeline is installed, complete and ready barring the 90 meters pending stretch. It could be that this is excess pipe and due to debris, garbage dumping and cars being parked, I could not make out if mole trenches are present. I am given to understand that an inspection is planned shortly. Should there be any updates, this page will be updated post the inspection over the next couple of days.
Photos of the pipes in the locations mentioned above(are these excess of installed pipes, or awaiting installation)
There is also a 300 meter internal stretch for B-Blocks that requires manual digging owing to electrical lines and they will proceed with caution with this stretch. This was brought up in my tele-meeting with GAIL today.
This will be done in 2 phases, for early applicants: Phase 1, who already have the meter installed. Phase 2: those who have applied, have received a BP number but don't have meters/internal pipelines installed. Both these phases are expected to close before Dec'25/ Jan 2026. If the activity moves without many impediments, we may even see GAS reaching South City around late November 2025.
Request residents to be patient and await further information. The process of laying and final connection to households are completely being managed by GAIL. timelines are indicative, GAIL is working with multiple govt agencies, impediments could come up and get resolved quickly or could take time. SUGRUHA has been coordinating and facilitating with all agencies involved to expedite the process as much as can be done. Thanks for your understanding.
- 04/Oct/2025: Update from GAIL Gas representative:
1. External Pipeline laying activity from RBI/Gaurav Nagar to South City: The previous external piping contractor was replaced, The new vendor has being appointed and should start work approx by 5th of October 2025, expected to take about a month leading to a date of mid of November 2025. The pipeline digging will start from Gaurav Nagar (near Elita) via mini forest, Balaji service station road to Southcity.
2. Safe digging: Some of the areas where BESCOM underground lines are expected to exist, will require manual digging to avoid short circuit as faced earlier in July.
3. The internal pressure test in all building was performed early September 2025.
4. Pending meter installation and internal work: will be resumed once the gas pipeline (point1) reaches South city, expected mid Jan 2026
I made a humble request was made during a Bhoomi Pooja, where the MP and GAIL officials were present, near Konankunte, on 28th August 2025, that work be expedited while ensuring safety and standard procedure is followed.
Continuous followup on a daily basis is in progress